Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?

  1. Control key
  2. Confirmation key
  3. Scheduling key
  4. Customizing key

Answer(s): A



In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?

  1. Automatic requirement grouping indictor
  2. MRP element indicator
  3. MRP groups
  4. Material group

Answer(s): B



What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

  1. The "project stock" indicator is set in the project definition (either valuated or non- valuated)
  2. The "Valuated project stock" indicator must be set in the project definition.
  3. The MRP group of the components must permit requirements grouping.
  4. The project must be released.
  5. The top-level WBS element must be released.

Answer(s): B,C



In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?

  1. Available to promise check
  2. Available on booking check
  3. Available on requirement check
  4. Immediate delivery check

Answer(s): A