Free SAP C_TS412_2021 Exam Questions (page: 4)

Your customer wants to use requirements grouping in SAP Project System.
What are the prerequisites for requirements grouping of materials?
Note: There are 2 correct answers to this question

  1. The materials must allow sales order or project stock
  2. The exact lot size procedure must be used
  3. The procurement type of the material must be internal
  4. An MRP group must be assigned

Answer(s): A,D

Explanation:

Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy.


Reference:

https://help.sap.com/doc/78f5c353b677b44ce10000000a174cb4/700_SFIN20%20006/en- US/0814c353b677b44ce10000000a174cb4.html



You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center?
Note: There are 2 correct answers to this question

  1. Maintain subordinate internal activity elements assigned to other work centres
  2. Increase the capacities of the work center in the project planning board.
  3. Trigger automatic capacity leveling inside the project planning board
  4. Shift activities backward or forward on the time axis where more capacities are available

Answer(s): C,D

Explanation:

Capacity requirements are the demand for capacities that result from planned or actual orders. If a work center is overloaded, it means that its capacity requirements exceed its available capacities. To reduce the overload of the work center, you can trigger automatic capacity leveling inside the project planning board, which is a tool that allows you to plan and monitor capacities for network activities.

You can also shift activities backward or forward on the time axis where more capacities are available, which means changing their start and finish dates manually or automatically.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



A customer needs to analyze the capacity requirements of their network activities.
Which reports do you recommend?
Note: There are 2 correct answers to this question

  1. Resource reports
  2. Cost element reports
  3. Structure information system reports
  4. Hierarchical reports

Answer(s): A,D

Explanation:

Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish?
Note: There are 2 correct answers to this question

  1. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
  2. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
  3. You can always maintain the actual start and finish date of a WBS element
  4. You can only maintain the actual start of a WBS element if the finish date is not maintained

Answer(s): B,C

Explanation:

If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-

US/6a7a9f0a6e421014e10000000a174cb4.html