What functions are available for period end closing in SAP Project System?
Note: There are 3 correct answers to this question

  1. Settlement
  2. Milestone trend analysis
  3. Confirmations
  4. Progress analysis
  5. Results analysis

Answer(s): A,D,E

Explanation:

Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Where can you assign the use status profile for WBS elements?
Note: There are 3correct answers to this question

  1. In the project profile
  2. In the project version
  3. In the project type
  4. In the project definition of a standard WBS
  5. In the operative WBS element

Answer(s): A,C,E

Explanation:

User status profiles are used to define additional statuses for project objects that can control their business processes. You can assign user status profiles for WBS elements in the project profile, which is a template for creating projects with similar characteristics. You can also assign user status profiles for WBS elements in the project type, which is a classification of projects according to their objectives and characteristics. You can also assign user status profiles for WBS elements in the operative WBS element itself, which is a structural element of a project that represents a task or a partial task.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which organizational structures are required for network activities?
Note: There are 3 correct answers to this question

  1. Controlling area
  2. Plant
  3. Sales organization
  4. Company code
  5. Operating concern

Answer(s): A,B,D

Explanation:

Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which sets of dates can be used to schedule networks?
Note: There are 2 correct answers to this question

  1. Basic dates
  2. Forecast dates
  3. Baseline dates
  4. Planned dates

Answer(s): A,D

Explanation:

Basic dates and planned dates are some of the sets of dates that can be used to schedule networks. Basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. Planned dates are the scheduled start and finish dates of an activity or a network, based on its basic dates and available capacities.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html