Which master data object governs the relationship between supply source and demand source in the Kanban process?

  1. Control cycle
  2. Production supply area
  3. Replenishment strategy
  4. Rate routing

Answer(s): A



Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?

  1. Posting of production costs to the production cost collector
  2. Material staging for nex order in sequence
  3. Archiving of documents for assembly scrap
  4. Posting of goods receipt for the product
  5. Reduction of associated capacity requirements

Answer(s): A,D,E



You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.

What must you do?

  1. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  2. Set the creation indicator for purchase requisitions on initial screen of MRP run
  3. Add the agreement to the source list and mark it for MRP revalance.
  4. Add the agreement to the quota arrangement and mark it for MRP revalance.

Answer(s): A,C



When do you use variant bills of materials (BOMs)?

  1. When a material has a configurable BOM
  2. When multiple materials also have similar BOMs
  3. When a material has multiple BOMs
  4. When multiple materials have multiple BOMs

Answer(s): D