What sequence do you follow in master data maintenance to define the production of a material?

  1. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
  2. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
  3. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
  4. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing

Answer(s): D



In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.

What does a firming type define? (Choose two)

  1. Handling existing procurement proposals outside the planning time fence.
  2. Handling existing procurement proposals within a planning time fence.
  3. Handling new requirements within the planning time fence.
  4. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.

Answer(s): B,D



What do you have to consider when you use SAP ECC long-term planning (LTP)? (Choose two)

  1. A planning scenario must be released before it can be used in LTP.
  2. Reorder point planned materials can be included in LTP.
  3. LTP focuses on the operational planning of important components.
  4. LTP creates purchase requisitions for external procurement.

Answer(s): A,B



Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order?

  1. The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements.
  2. An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts.
  3. The ATP quantity is the quantity still available that can be used to confirm incoming customer orders.
  4. If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time.

Answer(s): C



Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?

  1. D (document item)
  2. E (external procurement)
  3. M (phantom material)
  4. N (non-stock item)

Answer(s): D