Which property applies for consumption with planning strategy 40 (planning with final assembly)?

  1. Consumption can result in subsequent adjustments of planned receipts.
  2. Consumption can reduce the originally planned production quantity.
  3. Consumption takes place with the planning material.
  4. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.

Answer(s): A



Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)

  1. Task list
  2. Work center
  3. Production version
  4. Bill of material
  5. Material master

Answer(s): A,D,E



A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently

processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists. What do you have to consider for the two lists at this stage? (Choose two)

  1. The stock/requirements list was updated the moment it was accessed.
  2. The MRP list displays the production order.
  3. The MRP list has the status "processed".
  4. The stock/requirements list displays the production order.

Answer(s): A,D



Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)

  1. MPS items are planned in a standard MRP run.
  2. The planning of MPS and non-MPS items is always carried out in one planning run.
  3. Non-MPS items can be taken into consideration by an MPS run.
  4. MPS items can be defined on plant level.
  5. MPS items can be defined on MRP area level.

Answer(s): C,D,E



You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling). Which of the following properties for the resulting dependent requirements applies?

  1. In multi-level backward scheduling, dependent requirements are calculated to the exact second.
  2. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.
  3. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
  4. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

Answer(s): D