The Development Team has suggested to move the Daily Scrum to every other day instead of every day. What is the most appropriate action for the Scrum Master to take?

  1. Learn why the Development Team wants this, coach the team on why the Daily Scrum is important and work with them to improve the outcome of the Daily Scrum.
  2. Support the self-organizing team’s decision.
  3. Have the Development Team members vote on which days the Daily Scrum should occur.

Answer(s): A

Explanation:

The Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Guide. Scrum Masters do this by helping everyone understand Scrum theory, practices, rules, and values.



What action can the Scrum Master take to ensure communication between the Development Team and Product Owner is effective?

  1. Ensure all communication goes through the Scrum Master first.
  2. Teach the Product Owner to talk in terms of technology and technical requirements.
  3. Observe the communications between them and facilitate discussions if needed or by request.
  4. Translate the technologies used by the Development Team in order for the Product Owner to make decisions.

Answer(s): C

Explanation:

One of the primary responsibilities of a Scrum Master is the ability to facilitate regardless of the context or setting.



On a project where multiple Scrum Teams are working from the same Product Backlog, how should the work be distributed between teams?

  1. The Scrum Team with the highest capacity will pull items from the Product Backlog first.
  2. Each Scrum Team must have an equal amount of User Stories per Sprint.
  3. The Product Owner separates the Product Backlog items for each team.
  4. The Development Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.

Answer(s): D

Explanation:

During Sprint Planning the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team regardless of the number of Development Teams working from the same Product Backlog. Only the Development Team can assess what it can accomplish over the upcoming Sprint.



The outcome of a Sprint can be impacted by which of the following? (Choose all that apply.)

  1. The working relationships and skills of the people on the Scrum Team(s).
  2. The complexity and stability of the technology.
  3. The complexity of the requirements.

Answer(s): A,B,C

Explanation:

The knowledge, skills, behaviors of the team, and what’s known and not known will impact not only how effective the team is but also the outcomes of what it can produce.