In what ways does the Scrum Master keep a Development Team working at its highest level of productivity?

  1. By removing impediments that hinder the Development Team and facilitating Development Team decisions.
  2. By helping the Development Team with user acceptance tests and tracking defects.
  3. By ensuring each member takes turns speaking at the Daily Scrum and ending the event on time.
  4. By keeping the Scrum board and burn-down chart updated daily.

Answer(s): A

Explanation:

The Scrum Master serves the Development Team by removing impediments to the Development Team’s progress and facilitating Scrum events as requested or needed.



Which of the following statements are true about the Scrum Master role?

  1. The Scrum Master assigns the tasks to Development Team members and ensures they are completed within the committed timebox.
  2. The Scrum Master helps those outside the Scrum Team understand which interactions are helpful and teaches the Development Team to keep the Scrum meetings within the timebox.
  3. The Scrum Master is responsible for updating the Scrum board and ensuring team members avoid conflicts.
  4. At the Sprint Review, the Scrum Master demonstrates the completed Increment and answers any questions from the stakeholders.

Answer(s): B

Explanation:

The Scrum Master is responsible not only for coaching the Scrum Team but also the organization.



A Development Team, that has remote team members, typically spends time before the Daily Scrum to setup the meeting rooms and conference calling equipment and tools in order to have their Daily Scrum.
How should the Scrum Master handle this situation?

  1. Allow the Development Team to self-manage and decide for itself what to do.
  2. Setup the meeting and tell the Development Team that is how it will be done.
  3. Ask the Development Team members to alternate who is responsible for meeting setup.
  4. Inform management and ask them to solve it.

Answer(s): A

Explanation:

As a self-organized team, they will decide for themselves how to best manage communication between team members. The Scrum Master will only take action if requested OR if he/she observes that there is a potential problem.



A Development Team member has notified the Scrum Master of a potential data security risk. What action should the Scrum Master take?

  1. Notify the test team.
  2. Add a Product Backlog item to address the security issue.
  3. Ask the Development Team member to share the issue with the team as soon as possible.
  4. Wait until the Sprint Retrospective to add security to the definition of “Done”.

Answer(s): C

Explanation:

It is best to coach the Development Team members to collaborate on issues regardless of severity. They may consult the Scrum Master of Product Owner if needed.