Test Prep CFA-Level-I Exam
CFA® Level I Chartered Financial Analyst (Page 10 )

Updated On: 19-Jan-2026

A firm's preferred equity has a face value of 100 and a 5.5% coupon. The equity is trading at $87.29 per share. The firm is in the 40% tax bracket. Its cost of preferred stock equals ________.

  1. 2.52%
  2. 3.30%
  3. 6.30%
  4. 3.78%

Answer(s): C

Explanation:

Preferred dividends are not tax-deductible. Hence, no tax adjustment is made while calculating the cost of preferred equity. The price of a perpetuity that pays C per year, at a discount rate of R, equals C/R. Hence, 87.29 = 5.5/R, giving R = 6.3%.



The common stock of Anthony Steel has a beta of 1.20. The risk-free rate is 5 percent, and the market risk premium is 6 percent. This year's addition to retained earnings is $3,000,000. The company's capital budget is $4,000,000 and its target capital structure is 50 percent debt and 50 percent equity. What is the company's cost of equity financing?

  1. 12.4%
  2. 7.0%
  3. 11.0%
  4. 12.2%
  5. 7.2%

Answer(s): D

Explanation:

Anthony Steel will use retained earnings to fund the equity portion of its capital budget. We can see this because the retained earnings break point is $3,000,000/0.5 = $6,000,000, which is greater than the capital budget.
The cost of equity from the CAPM (Capital Asset Pricing Model) is:
k(s) = krf) + (k(m) - k(rf))b(i) = 5% + (6%)1.2 = 12.2%.



Assume that a firm has a degree of financial leverage of 1.25. If sales increase by 20 percent, the firm will experience a 60 percent increase in EPS, and it will have an EBIT of $100,000. What will be the EBIT for this firm if sales do not increase?

  1. $42,115
  2. $84,375
  3. $67,568
  4. $100,000
  5. $113,412

Answer(s): C

Explanation:

DTL = % change EPS/% change Sales = 60%/20% = 3.0.
DOL = DTL/DFL = 3.0/1.25 = 2.40.
Old EBIT = $100,000/[1 + (0.20)(2.40)] = $100,000/1.48 = $67,568.
Alternate solution:
Use DFL expression to calculate change in EBIT and previous EBIT:
DFL = 1.25 = %change EPS/%change EBIT
= 0.60/[change EBIT/($100,000 - change EBIT)]
= [0.60($100,000) - 0.60(change EBIT)]/change EBIT
1.25 change EBIT = $60,000 - 0.60(change EBIT)
1.85 change EBIT = $60,000
change EBIT = $32,432.
Old EBIT = $100,000 - $32,432 = $67,568.



Returns on the market and Takeda Company's stock during the last 3 years are shown below:
YearMarketTakeda
1995-12%-14%
19962331
19971610
The risk-free rate is 7 percent, and the required return on the market is 12 percent. Takeda is considering a project whose market beta was found by adding 0.2 to the company's overall corporate beta. Takeda finances only with equity, all of which comes from retained earnings. The project has a cost of $100 million, and it is expected to provide cash flows of $20 million per year at the end of Years 1 through 5 and then $30 million per year at the end of Years 6 through 10. What is the project's NPV (in millions of dollars)?

  1. $23.11
  2. $22.55
  3. $28.12
  4. $20.89
  5. $25.76

Answer(s): A

Explanation:

1. Run a regression to find the corporate beta. It is 1.1633.
2. Find the project's estimated beta by adding 0.2 to the corporate beta. The project beta is thus 1.3633.
3. Find the company's cost of equity, which is its WACC because it uses no debt: k(s) = WACC = 7% + (12% - 7%)1.3633 = 13.8165%.
4. Now find NPV (in millions):
CF(0) = -100
CF(1-5) = 20
CF(6-10) = 30
I = 13.82 Solve for NPV = $23.11 million.



Which of the following statements is correct?

  1. Only if one attempts to calculate MIRRs does one have to worry about multiple IRRs.
  2. The discounted payback is generally shorter than the regular payback.
  3. The NPV and IRR methods can lead to conflicting accept/reject decisions only if (1) mutually exclusive projects are being evaluated and (2) if the projects' NPV profiles cross at a rate less than the firm's cost of capital.
  4. The NPV and IRR methods can lead to conflicting accept/reject decisions only if (1) mutually exclusive projects are being evaluated and (2) if the projects' NPV profiles cross at a rate greater than the firm's cost of capital.
  5. Any type of project might have multiple rates of return if the IRR is sufficiently high.

Answer(s): C

Explanation:

The two conditions which can cause NPV profiles to cross, and thus conflicts to arise between NPV and IRR: 1) when project size differences exists, or 2) when timing differences exist.



Viewing page 10 of 793
Viewing questions 46 - 50 out of 3963 questions



Post your Comments and Discuss Test Prep CFA-Level-I exam prep with other Community members:

Join the CFA-Level-I Discussion