Free CPIM Exam Braindumps
Certified in Production and Inventory Management Questions 226–230 (page: 47)

Updated On: 9-Feb-2026

1. Determine the standard hours of operation time for each planned and released order for each work center by time period.
2. Add all the standard hours together for each work center in each period. These are the steps of calculating:

  1. load
  2. Capacity required
  3. Available capacity
  4. None of these

Answer(s): A,B



______________ is a usual process to start with the due date and using find lead time, to work back to operations?

  1. Efficiency
  2. Utilization
  3. Back Scheduling
  4. Capacity management

Answer(s): C



For back scheduling we need to know?

  1. Quantity and due date
  2. Sequence of operations and Work centers needed
  3. Setup and run time for each operation
  4. All of these

Answer(s): D



In back scheduling, Sequence of operation, Work centers needed setup time, and runtime are included in a/an?

  1. Order file
  2. Work Center file
  3. Route file
  4. Load Sheet

Answer(s): C



Alter the load or the change the capacity awareness. These are the two ways of:

  1. Balancing capacity
  2. Balancing capacity required
  3. Balancing capacity available
  4. All of these

Answer(s): C