Capacity planning links the various production priority schedules to :

  1. Manufacturing plans
  2. Manufacturing resources
  3. MRP
  4. All of these

Answer(s): B



_____________ is the process of monitoring production output, comparing it with capacity plans, and taking corrective action when needed.

  1. Capacity control
  2. Capacity planning
  3. Capacity required
  4. Capacity management

Answer(s): A



"The function of establishing, measuring, monitoring and adjusting limits or levels of capacity in order to execute all manufacturing schedules". This definition is related to:

  1. Capacity planning
  2. Capacity control
  3. Capacity management
  4. None of these

Answer(s): C



Which of the following steps is NOT included in capacity planning?

  1. Determine the capacity available at each work center in each time period.
  2. Determine the load at each work center in each time period
  3. Resolve differences between available capacity to match the load. Otherwise, the priority plans must be changed to match the available capacity
  4. None of these

Answer(s): D