If the efficiency of the work center in the above question is 115%. What is the rated capacity of the work center?

  1. 287 Standard hours per week
  2. 276 Standard hours per week
  3. 279 Standard hours per week
  4. None of these

Answer(s): B



Over a period of 4 weeks, a work center produced 50, 45, 40, and standard house of work. What is the demonstrated capacity of the work center?

  1. 47.8
  2. 47.5
  3. 48
  4. 49.5

Answer(s): A



In 1 week, a work center produces 85 standard hours of work. The hours scheduled are 80, and 75 hours are actually worked. Calculate the utilization and efficiency of the work center.

  1. 93.75% and 113.33%
  2. 97.75% and 113.33%
  3. 93.75% and 110.33%
  4. None of the above

Answer(s): A



How many standard hours are needed to run an order of 200 pieces if the setup time is 1.3 hours and the run time 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency.130% and the utilization is 70%?

  1. 51.3 standard hours; 67.4 actual hours
  2. 62 standard hours; 60.4 actual hours
  3. 61.3 standard hours; 67.4 actual hours
  4. 61.3 standard hours; 60.4 actual hours

Answer(s): C



Production activity control is responsible for executing the:

  1. Production Schedule
  2. MRP
  3. Both of these
  4. Capacity control

Answer(s): C



Viewing page 49 of 119
Viewing questions 241 - 245 out of 588 questions