If the efficiency of the work center in the above question is 115%. What is the rated capacity of the work center?
Answer(s): B
Over a period of 4 weeks, a work center produced 50, 45, 40, and standard house of work. What is the demonstrated capacity of the work center?
Answer(s): A
In 1 week, a work center produces 85 standard hours of work. The hours scheduled are 80, and 75 hours are actually worked. Calculate the utilization and efficiency of the work center.
How many standard hours are needed to run an order of 200 pieces if the setup time is 1.3 hours and the run time 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency.130% and the utilization is 70%?
Answer(s): C
Production activity control is responsible for executing the: