Any changes can be made to the MPS as long as it is within the limits set by the production plan. Changes are routine and are often made by the computer program.
This is the scenario in zone of time fence.

  1. Slushy Zone
  2. Frozen Zone
  3. Liquid Zone
  4. None of these

Answer(s): C



1. Wrong product or specification
2. Wrong amount (too little or too much)
3. Wrong shipping date (too early or too late)

These are common errors __________ in that occur all the time and require constant attention.

  1. Customer Expectations
  2. Customer orders
  3. MPS
  4. MRP

Answer(s): B



___________is a rate of doing work, not the quantity of work done.

  1. Capacity
  2. Capacity Planning
  3. Capacity Control
  4. Capacity required

Answer(s): A



A term closely related to capacity required is ___________ . This is the amount of released and planned work assigned to a facility for a par.

  1. Capacity available
  2. Target capacity
  3. Load
  4. Output

Answer(s): C