The project management plan:

  1. justifies undertaking the project.
  2. describes the success criteria for the project.
  3. focuses primarily on time related issues.
  4. describes the success factor for the project.

Answer(s): B



The project management plan is:

  1. owned by the Project Manager and the project team.
  2. owned by the sponsor.
  3. owned by the Project Manager.
  4. owned by the Project Manager and the project stakeholders.

Answer(s): C



Which structure shows the reporting relationships and communications channels for a project?

  1. Work breakdown structure.
  2. Organisational breakdown structure.
  3. Product breakdown structure.
  4. Responsibility assignment structure

Answer(s): B



Scheduling can best be defined as the process used to determine:

  1. overall project duration.
  2. project cost.
  3. the project management plan.
  4. sub-contractor's responsibilities

Answer(s): A



Which one of the following statements best describes resource scheduling?

  1. process which identifies activities that will need project resources.
  2. A. process to assign roles to project resources.
  3. A. process that identifies when resources are needed.
  4. A. process to estimate the project resources.

Answer(s): C