Which one of the following statements is correct?

  1. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.
  2. Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.
  3. Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.
  4. Quality planning enables the project manager to manage the trade-off between customer expectations and budget.

Answer(s): C



The business case is owned by the project:

  1. manager.
  2. sponsor.
  3. steering group (board).
  4. senior user.

Answer(s): B



Which one of the following would NOT typically be part of procurement?

  1. Estimating.
  2. Engagement of external suppliers.
  3. Definition of items to be acquired.
  4. Bidding.

Answer(s): A



Which one of the following is the best reason for splitting a project into phases?

  1. For team members to reflect on their performance during a phase.
  2. For the project manager to take a break between phases.
  3. It creates a decision point for continuing the project.
  4. In order for the plan to be updated regularly.

Answer(s): C



Which one of the following is NOT part of the handover process during the final phase of a project lifecycle:

  1. the acceptance of pertinent documentation relative to project deliverables.
  2. the definition of acceptance criteria for project deliverables.
  3. the transfer of responsibility for project deliverables.
  4. the testing of project deliverables to demonstrate they work in their final operational mode.

Answer(s): B