What is meant by the term programme management?

  1. The management of group of projects or activities that have a common business aim.
  2. The line management of A. team of programme managers.
  3. The management of A. functional are aused by a number of different projects.
  4. The management of the programme of activities identified in the project plan

Answer(s): A



A responsibility assignment matrix (RAM) allows the project manager to cross reference:

  1. the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks.
  2. the organisational breakdown structure (OBS) with the cost breakdown structure (CBS) to assign A.
    cost to each resource.
  3. the product breakdown structure (PBS) with the work breakdown structure (WBS) to assign activities to the products.
  4. the organisational breakdown structure (OBS) with the product breakdown structure (PBS) to assign resources to deliverables.

Answer(s): A



Which one of the following is a valid description of the phases of a complete project lifecycle?

  1. Start-up, feasibility, planning, execution and roll-out.
  2. Concept, screening, implementation, handover and closeout.
  3. Concept, definition, implementation, handover and closeout.
  4. Start-up, definition, development and production closedown.

Answer(s): C



The main purpose of configuration management is to:

  1. minimise the impact of changes on the scope of the project.
  2. ensure that the final product meets the strategic needs of the business.
  3. provide control of the deliverables and avoid mistakes or misunderstandings.
  4. maximise the impact of agreed enhancements on the project deliverables.

Answer(s): C



The accuracy of an estimate should:

  1. decrease as a project progresses through its lifecycle.
  2. increase as a project progresses through its lifecycle.
  3. stay constant throughout the project.
  4. vary independently of where the project is in its lifecycle

Answer(s): B