A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources. Before initiating closeout and releasing the resources, what should the program manager do?
Answer(s): A
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.What should the program manager do next to address this risk?
Answer(s): D
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project scheduleWhat should the program manager do?
A program with objectives trial impact a large segment of the population receives negativecommentary from organizations representing the public interest What action should the program manager take first?
A program manager assigns project managers lo five component projects and continues to develop the program team.Which of the following represents the program manager's strategy?
Answer(s): B