Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

  1. EAC
  2. BAC
  3. CPI
  4. ETC

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231



The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?

  1. The project manager should identify and document the reasons for the additional resources in a change request.
  2. The project manager should hire additional resources temporarily to complete the project.
  3. The project manager should terminate the project until additional resources are added to the project.
  4. The project manager should ask the project team members to take on more tasks to complete the project on time.

Answer(s): A



An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

  1. PMO
  2. Project sponsor
  3. Project coordinator
  4. HR

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82



When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

  1. Issue log
  2. Risk management plan
  3. Communications plan
  4. Risk register
  5. Status report

Answer(s): D