Which of the following is a definition of an RFP?

  1. A document sent to potential vendors to solicit a bid for a project.
  2. A document sent to potential vendors to request information for skills and experience for a project.
  3. A document sent to potential vendors to request a commitment for a project.
  4. A document sent to potential vendors to solicit information that excludes pricing information for a project.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300



A customer has requested additional features for an active project. Which of the following steps should take place NEXT?

  1. Implement the requested changes.
  2. Evaluate the impact of the changes.
  3. Update all project documents.
  4. Submit the requested changes to the CCB.

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293



A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success.

Which of the following risk strategies should the project manager adopt?

  1. Exploitation
  2. Avoidance
  3. Acceptance
  4. Mitigation

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 239



A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.

Which of the following documents should the project manager create?

  1. Business case
  2. Project charter
  3. Scope statement
  4. Project management plan

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107



Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

  1. Sales clerk
  2. Marketing representative
  3. Team lead
  4. Product item

Answer(s): B