A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?

  1. Establish each WBS work package resource.
  2. Establish and set the baseline.
  3. Establish and set the quality gates.
  4. Establish the tollgates.

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 167



Which of the following describes how a project is related to a program?

  1. A program is a combination of multiple projects.
  2. A program contains an element of the project.
  3. A program is a part of a project.
  4. A program uses half of the project’s budget.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 72



Which of the following are examples of organizational change? (Choose two.)

  1. Relocation
  2. Scope
  3. Business process
  4. Schedule
  5. Risk event

Answer(s): A,C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297



A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

  1. Project schedule
  2. Cost plan
  3. Scope statement
  4. Impact assessment

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156