Free CompTIA PK0-004 Exam Braindumps (page: 33)

Which of the following vendor documents specifically address quality? (Choose two.)

  1. LOI
  2. SLA
  3. Warranty
  4. PO
  5. NDA

Answer(s): A,B



A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the work packages for the WBS?

  1. Brainstorming
  2. Analogous
  3. Bottom-up
  4. Forward pass

Answer(s): C



Which of the following documents need to be updated as events occur during a project? (Choose two.)

  1. Change request
  2. Risk register
  3. Meeting minutes
  4. Issue log
  5. Status report

Answer(s): C,E



During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

  1. Change request
  2. Risk mitigation
  3. Change control
  4. Scope creep

Answer(s): D