Free CompTIA PK0-004 Exam Questions (page: 34)

A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?

  1. Project schedule
  2. Action items
  3. Project charter
  4. Communication plan

Answer(s): A



A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

  1. Add durations.
  2. Add the start and finish dates
  3. Add tasks.
  4. Add resources.

Answer(s): C



A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

-Coordinate project schedule
-Manage to the triple constraint
-Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?

  1. Balanced matrix
  2. Strong matrix
  3. Functional
  4. Projectized

Answer(s): D



Which of the following shows projected project expenditures?

  1. Work breakdown structure
  2. Cash flow schedule
  3. Cash burn rate
  4. Budget milestone

Answer(s): A