A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)

  1. Using the WBS will help prevent work from slipping or being forgotten.
  2. TheWBS will be required on very large projects.
  3. TheWBS will be required if the project manager has the time available to complete it.
  4. TheWBS will aid in determining which resources are required for the project.
  5. The WBS is the best way to determine risks of the project.

Answer(s): A,D



A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

  1. Issue log
  2. Action items
  3. Dashboard information
  4. Communication plan

Answer(s): A



Which of the following elements should be included on a responsibility assignment matrix?

  1. Responsible, accountable, consulted, informed
  2. Resource, accountable, signoff, input
  3. Responsible, accurate, confidential, informed
  4. Resource, accountable, consulted, informed

Answer(s): A



The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?

  1. Project charter
  2. Project schedule
  3. Meeting agenda
  4. Responsibility assignment matrix
  5. Risk register

Answer(s): B