Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?

  1. WBS
  2. RACI
  3. RFP
  4. PERT

Answer(s): A



After a meeting, a team member recaps all of the topics that worked well, worked relatively well, and did not work at all. The expectation is for upcoming project work to make better progress and achieve targets. Which of the following combinations of tactics is being used?

  1. Stand-up meeting, action items
  2. Workshop meeting, timeboxing
  3. Status meeting, follow-ups
  4. Presentation meeting, meeting notes

Answer(s): C



In the middle of a five-year project, a vendor asked the buyer to revisit the rate card associated with the development team. According to the vendor, the development team's experience and technical skills have increased since the project started. Which of the following documents should the buyer review FIRST?

  1. MOU
  2. SOW
  3. RFP
  4. RFI

Answer(s): B



A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?

  1. Ask the sponsor for additional funding to accommodate the request.
  2. Escalate the request to the senior management team.
  3. Advise that a change request would need to be approved.
  4. Instruct the project team to set up the additional workstations.

Answer(s): C



During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?

  1. Create a change request for the change advisory board.
  2. Work with the business analyst to document the new epic.
  3. Reject the change to prevent scope creep.
  4. Update the risk register and the work in the mitigation plan.

Answer(s): A



Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?

  1. Negotiate to get more of the team member's available time.
  2. Assign the team member to work overtime to finish the task.
  3. Speed up completion of the task by assisting the team member.
  4. Have the project manager complete the task.

Answer(s): A



A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?

  1. Dashboard
  2. Status report
  3. Gantt chart
  4. Email

Answer(s): A



A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?

  1. Trust that the project requirements fully document the necessary compliances.
  2. Meet with the end users to learn more about the compliance requirements.
  3. Research the compliance requirements related to the project to understand the implications.
  4. Make the QA specialist responsible for ensuring that the compliance requirements are met.

Answer(s): C