CompTIA PK0-005 Exam Questions
CompTIA Project+ (Page 13 )

Updated On: 17-Feb-2026

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project.
Which of the following could MOST likely be the cause of this issue?

  1. A project manager assigned the wrong resources.
  2. A project manager did not release the resources
  3. A project manager did not remove the system access.
  4. A project manager did not provide the project sign-off.

Answer(s): B



Which of the following requires the MOST availability from the business team?

  1. SDLC
  2. Scrum
  3. PRINCE2
  4. Waterfall

Answer(s): B



Which of the following software programs would be BEST to use lo store information related to business transactions?

  1. Record management system
  2. Customer relationship management
  3. Enterprise resource planning
  4. Content management system

Answer(s): B



During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed.
Which of the following actions should the project manager MOST likely perform?

  1. Work with the project scheduler to update the project timeline.
  2. Communicate to the stakeholders about the updated timeline.
  3. Ask the development team to fast-track upcoming activities.
  4. Add two resources so the critical activities will finish on time.

Answer(s): A



Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

  1. Memorandum of understanding
  2. Request for information
  3. Statement of work
  4. Non-disclosure agreement

Answer(s): B






Post your Comments and Discuss CompTIA PK0-005 exam dumps with other Community members:

Join the PK0-005 Discussion