During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed.
Which of the following actions should the project manager MOST likely perform?
- Work with the project scheduler to update the project timeline.
- Communicate to the stakeholders about the updated timeline.
- Ask the development team to fast-track upcoming activities.
- Add two resources so the critical activities will finish on time.