Free PK0-005 Exam Braindumps (page: 22)

Page 21 of 53

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

  1. Smoke testing
  2. Regression testing
  3. Unit testing
  4. User acceptance testing

Answer(s): B



A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

  1. Secure folder
  2. Real-time, multiauthoring editing software
  3. Digital whiteboard
  4. Wiki knowledge base

Answer(s): D



During online, collaborative meeting sessions, a project team is consistently in consensus, which is causing a creativity roadblock. Which of the following can the facilitator do to minimize this issue?

  1. Enable chat.
  2. Distribute surveys.
  3. Meet face to face.
  4. Use a whiteboard.

Answer(s): A



During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?

  1. Waterfall method
  2. Simulation method
  3. Precedence diagramming method
  4. Critical path method

Answer(s): C






Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

PK0-005 Discussions & Posts