Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

  1. 100
  2. 120
  3. 1,000
  4. 1,200

Answer(s): A



Which stakeholder approves a project's result?

  1. Customer
  2. Sponsor
  3. Seller
  4. Functional manager

Answer(s): A



Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  1. Collect Requirements
  2. Plan Scope Management
  3. Define Scope
  4. Define Activities

Answer(s): A



Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  1. Available organizational assets
  2. Project staff assignments
  3. Interpersonal skills
  4. Enterprise environmental factors

Answer(s): A



Perform Integrated Change Control is the process of:

  1. Reviewing, approving, and managing all change requests
  2. Facilitating change management, manuals, or automation tools
  3. Comparing actual results with planned results in order to expand or change a project
  4. Documenting changes according to the change control system by the change control board

Answer(s): A