The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

  1. recognition and rewards
  2. compliance
  3. staff acquisition
  4. training needs

Answer(s): D



Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

  1. Continuous
  2. Discrete
  3. Regulated
  4. Arbitrary

Answer(s): A



A graphic display of project team members and their reporting relationships is known as a:

  1. Resource calendar.
  2. Project organization chart.
  3. Resource breakdown structure (RBS).
  4. Responsibility assignment matrix (RAM).

Answer(s): B



Which item is a cost of conformance?

  1. Training
  2. Liabilities
  3. Lost business
  4. Scrap

Answer(s): A



Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

  1. Collaboration
  2. Negotiation
  3. Decision making
  4. Influencing

Answer(s): D