The following chart contains information about the tasks in a project.



Based on the chart, what is the cost variance (CV) for Task 6?

  1. -2,000
  2. 0
  3. 1,000
  4. 2,000

Answer(s): D



The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

  1. Acquire Project Team.
  2. Plan Human Resource Management.
  3. Manage Project Team.
  4. Develop Project Team.

Answer(s): A



The scope management plan and scope baseline are contained in:

  1. organizational process assets
  2. a requirements traceability matrix
  3. the project charter
  4. the project management plan

Answer(s): D



Which Manage Communications tool or technique focuses on identifying and managing barriers?

  1. Communication methods
  2. Information technology
  3. Communication models
  4. Information management systems

Answer(s): C



Which type of organizational structure is displayed in the diagram provided?

  1. Balanced matrix
  2. Projectized
  3. Strong matrix
  4. Functional

Answer(s): B