Which type of graphic is displayed below?

  1. Work breakdown structure
  2. Context diagram
  3. Control chart
  4. Pareto diagram

Answer(s): A



An example of a group decision-making technique is:

  1. nominal group technique
  2. majority
  3. affinity diagram
  4. multi-criteria decision analysis

Answer(s): B



Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

  1. Procurement documents
  2. Inspection and audits
  3. Estimate budget
  4. Risk register

Answer(s): B



Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

  1. Influencing
  2. Motivation
  3. Negotiation
  4. Trust building

Answer(s): B