The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?
Answer(s): A
The following is a network diagram for a project.The critical path for the project is how many days in duration?
Answer(s): D
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be: