The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?

  1. 10
  2. 12
  3. 14
  4. 16

Answer(s): A



The following is a network diagram for a project.



The critical path for the project is how many days in duration?

  1. 10
  2. 12
  3. 14
  4. 17

Answer(s): D



The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

  1. recognition and rewards
  2. compliance
  3. staff acquisition
  4. training needs

Answer(s): D



Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

  1. Continuous
  2. Discrete
  3. Regulated
  4. Arbitrary

Answer(s): A