GAQM APM-001 Exam Questions
Associate in Project Management (APM) (Page 9 )

Updated On: 24-Feb-2026

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  1. Estimate Costs
  2. Control Costs
  3. Plan Cost Management
  4. Determine Budget

Answer(s): D



In project management, a temporary project can be:

  1. Completed without planning
  2. A routine business process
  3. Long in duration
  4. Ongoing to produce goods

Answer(s): C



Which document in the project management plan can be updated in the Plan Procurement Management process?

  1. Budget estimates
  2. Risk matrix
  3. Requirements documentation
  4. Procurement documents

Answer(s): C



Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

  1. Uniform
  2. Continuous
  3. Discrete
  4. Linear

Answer(s): C



Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  1. Update
  2. Preventive action
  3. Defect repair
  4. Corrective action

Answer(s): D






Post your Comments and Discuss GAQM APM-001 exam dumps with other Community members:

Join the APM-001 Discussion