A project manager should communicate to stakeholders about resolved project issues by updating the:

  1. project records
  2. project reports
  3. stakeholder notifications
  4. stakeholder register

Answer(s): C



Which Project Time Management process includes bottom-up estimating as a tool or technique?

  1. Estimate Activity Resources
  2. Sequence Activities
  3. Estimate Activity Durations
  4. Develop Schedule

Answer(s): A



Progressively elaborating high-level information into detailed plans is performed by the:

  1. project management office
  2. portfolio manager
  3. program manager
  4. project manager

Answer(s): D



An input to the Control Quality process is:

  1. Activity attributes
  2. Quality control measurements
  3. Enterprise environmental factors
  4. Deliverables

Answer(s): D



The chart below is an example of a:

  1. Responsibility assignment matrix (RAM)
  2. Work breakdown structure (WBS)
  3. RACI chart
  4. Requirements traceability matrix

Answer(s): D