Which element does a project charter contain?

  1. Management reserves
  2. Work breakdown structure
  3. Stakeholder list
  4. Stakeholder register

Answer(s): C



The following is a network diagram for a project.



What is the critical path for the project?

  1. A-B-C-F-G-I
  2. A-B-C-F-H-I
  3. A-D-E-F-G-I
  4. A-D-E-F-H-I

Answer(s): A



The following is a network diagram for a project.



How many possible paths are identified for this project?

  1. 3
  2. 4
  3. 6
  4. 7

Answer(s): B



The following chart contains information about the tasks in a project.



Based on the chart, what is the schedulevariance (SV) for Task 8?

  1. -2,000
  2. -1,000
  3. 1,000
  4. 2,000

Answer(s): B



The following is a network diagram for a project.



The free float for Activity H is how many days?

  1. 4
  2. 5
  3. 10
  4. 11

Answer(s): A