Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

  1. project documents updates.
  2. project management plan updates.
  3. change requests.
  4. work performance information.

Answer(s): D



The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

  1. adaptive
  2. reflexive
  3. predictive
  4. iterative

Answer(s): A



Whose approval may be required for change requests after change control board (CCB) approval?

  1. Functional managers
  2. Business partners
  3. Customers or sponsors
  4. Subject matter experts

Answer(s): C



The primary benefit of the Plan Schedule Management process is that it:

  1. provides guidance to identify time or schedule challenges within the project.
  2. tightly links processes to create a seamless project schedule.
  3. guides how the project schedule will be managed throughout the project.
  4. creates an overview of all activities broken down into manageable subsections.

Answer(s): C



Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

  1. Influence/impact grid
  2. Power/influence grid
  3. Power/interest grid
  4. Salience model

Answer(s): C