GAQM APM-001 Exam
Associate in Project Management (APM) (Page 2 )

Updated On: 1-Feb-2026

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

  1. Analysis
  2. Appetite
  3. Tolerance
  4. Response

Answer(s): C



Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

  1. Critical path method
  2. Critical chain method
  3. Resource leveling
  4. Schedule network analysis

Answer(s): B



When closing a project or phase, part of the process may require the use of which type of analysis?

  1. Reserve analysis
  2. Regression analysis
  3. Document analysis
  4. Product analysis

Answer(s): B



In a typical project, project managers spend most of their time:

  1. Estimating
  2. Scheduling
  3. Controlling
  4. Communicating

Answer(s): D



For a stakeholder with low interest and high power, the project manager should:

  1. Monitor the stakeholder.
  2. Manage the stakeholder closely.
  3. Keep the stakeholder satisfied.
  4. Keep the stakeholder informed.

Answer(s): C



Viewing page 2 of 112
Viewing questions 6 - 10 out of 704 questions



Post your Comments and Discuss GAQM APM-001 exam prep with other Community members:

Join the APM-001 Discussion