Free APM-001 Exam Braindumps (page: 2)

Page 1 of 139

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

  1. Analysis
  2. Appetite
  3. Tolerance
  4. Response

Answer(s): C



Project deliverables that have been completed and checked for correctness through the Control

Quality process are known as:

  1. Verified deliverables.
  2. Validated deliverables.
  3. Acceptance criteria.
  4. Activity resource requirements.

Answer(s): A



An output of the Perform Integrated Change Control process is:

  1. Deliverables.
  2. Validated changes.
  3. The change log.
  4. The requirements traceability matrix.

Answer(s): C



During which process does the project team receive bids and proposals?

  1. Conduct Procurements
  2. Plan Procurements
  3. Estimate Costs
  4. Control Budget

Answer(s): A






Post your Comments and Discuss GAQM APM-001 exam with other Community members:

APM-001 Discussions & Posts