Project Scope Management is primarily concerned with:

  1. Developing a detailed description of the project and product.
  2. Determining how requirements will be analyzed, documented, and managed.
  3. Defining and controlling what is and is not included in the project.
  4. Formalizing acceptance of the completed project deliverables.

Answer(s): C



A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

  1. Strong
  2. Weak
  3. Managed
  4. Balanced

Answer(s): D



A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

  1. triangular distribution
  2. tornado diagram
  3. beta distribution
  4. fishbone diagram

Answer(s): B



Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  1. Identify Risks
  2. Plan Risk Management
  3. Perform Qualitative Risk Analysis
  4. Perform Quantitative Risk Analysis

Answer(s): C



The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

  1. Earned value management.
  2. Forecasting.
  3. Critical chain methodology.
  4. Critical path methodology.

Answer(s): A