Which output is the approved version of the time-phased project budget?

  1. Resource calendar
  2. Scope baseline
  3. Trend analysis
  4. Cost baseline

Answer(s): D



The purpose of the Project Communications Management Knowledge Area is to:

  1. Monitor and control communications throughout the entire project life cycle.
  2. Maintain an optimal flow of information among all project participants.
  3. Develop an appropriate approach for project communications.
  4. Ensure timely and appropriate collection of project information.

Answer(s): D



Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

  1. Level of control.
  2. Communication channels.
  3. Scope.
  4. Strategic alignment.

Answer(s): A



At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project.
Which item did this project create?

  1. Result
  2. Product
  3. Service
  4. Improvement

Answer(s): A



Power, urgency, and legitimacy are attributes of which stakeholder classification model?

  1. Salience
  2. Influence/impact
  3. Power/interest
  4. Power/influence

Answer(s): A