Power, urgency, and legitimacy are attributes of which stakeholder classification model?

  1. Salience
  2. Influence/impact
  3. Power/interest
  4. Power/influence

Answer(s): A



Through whom do project managers accomplish work?

  1. Consultants and stakeholders
  2. Stakeholders and functional managers
  3. Project team members and consultants
  4. Project team members and stakeholders

Answer(s): D



Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

  1. Checksheets
  2. Histograms
  3. Flowcharts
  4. Control charts

Answer(s): C



The following is a network diagram for a project.



The total float for the project is how many days?

  1. 5
  2. 9
  3. 12
  4. 14

Answer(s): B



The following is a network diagram for a project.



The free float for Activity E is how many days?

  1. 2
  2. 3
  3. 5
  4. 8

Answer(s): C