GAQM APM-001 Exam Questions
Associate in Project Management (APM) (Page 19 )

Updated On: 24-Feb-2026

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

  1. Acquire Project Team.
  2. Plan Human Resource Management.
  3. Manage Project Team.
  4. Develop Project Team.

Answer(s): A



At the start of a typical project life cycle, costs are:

  1. low, peak as work is carried out, and drop as the project nears the end.
  2. low, become steady as work is carried out, and increase as the project nears the end.
  3. high, drop as work is carried out, and increase as the project nears the end.
  4. high, become low as work is carried out, and drop as the project nears the end.

Answer(s): D



Success is measured by benefits realization for a:

  1. strategic plan
  2. project
  3. portfolio
  4. program

Answer(s): D



Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

  1. Plan Cost Management
  2. Plan Scope Management
  3. Plan Stakeholder Management
  4. Plan Schedule Management

Answer(s): C



A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

  1. Quality assurance.
  2. A stakeholder management plan.
  3. Project team building.
  4. Integrated change control.

Answer(s): D






Post your Comments and Discuss GAQM APM-001 exam dumps with other Community members:

Join the APM-001 Discussion