The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

  1. Define Activities.
  2. Sequence Activities.
  3. Define Scope.
  4. Control Schedule.

Answer(s): A



Which document includes the project scope, major deliverables, assumptions, and constraints?

  1. Project charter
  2. Project scope statement
  3. Scope management plan
  4. Project document updates

Answer(s): B



When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

  1. Bottom-up
  2. Parametric
  3. Analogous
  4. Three-point

Answer(s): A



Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

  1. Cost management plan
  2. Quality management plan
  3. Communications management plan
  4. Risk management plan

Answer(s): D



Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

  1. Organizational process assets
  2. A work breakdown structure
  3. The project management plan
  4. Enterprise environmental factors

Answer(s): A