Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

  1. Histograms
  2. Scatter diagrams
  3. Flowcharts
  4. Checksheets

Answer(s): D



The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

  1. start-to-start (SS)
  2. start-to-finish (SF)
  3. finish-to-start (FS)
  4. finish-to-finish (FF)

Answer(s): C



Work performance information and cost forecasts are outputs of which Project Cost Management process?

  1. Estimate Costs
  2. Plan Cost Management
  3. Determine Budget
  4. Control Costs

Answer(s): D



Which techniqe should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

  1. Coaching
  2. Avoidance
  3. Consensus
  4. Influencing

Answer(s): B



The procurement process that documents agreements and related documentation for future reference is known as:

  1. Plan Procurements.
  2. Control Procurements.
  3. Close Procurements.
  4. Conduct Procurements.

Answer(s): C