The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

  1. Supportive
  2. Leading
  3. Neutral
  4. Resistant

Answer(s): B



Which of the following is a narrative description of products, services, or results to be delivered by a project?

  1. Project statement of work
  2. Business case
  3. Accepted deliverable
  4. Work performance information

Answer(s): A



A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

  1. Historical information and the lessons-learned database.
  2. Historical information and the stakeholder register.
  3. Organizational process assets and the lessons-learned database.
  4. Project documents and historical information.

Answer(s): A



Projects are undertaken by an organization to support the:

  1. Product performance.
  2. Budget process.
  3. Collective capabilities.
  4. Organizational strategy.

Answer(s): D



What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

  1. 0.45
  2. 0.56
  3. 0.70
  4. 1.36

Answer(s): C



Viewing page 36 of 112
Viewing questions 176 - 180 out of 704 questions