Which of the following is contained within the communications management plan?

  1. An organizational chart
  2. Glossary of common terminology
  3. Organizational process assets
  4. Enterprise environmental factors

Answer(s): B



Which of the following is a tool and technique for Estimate Activity Durations?

  1. Parametric estimating
  2. Monte Carlo analysis
  3. Alternatives analysis
  4. Bottom-up estimating

Answer(s): A



Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

  1. Complete project phase
  2. Project life
  3. The project life cycle
  4. Project cycle

Answer(s): C



Which schedule network analysis technique modifies the project schedule to account for limited resources?

  1. Human resource planning
  2. Fast tracking
  3. Critical chain method
  4. Rolling wave planning

Answer(s): C



Which of the following is an output of the Monitor and Control Project Work process?

  1. Change requests
  2. Performance reports
  3. Organizational process assets
  4. Project management plan

Answer(s): A