Which of the following is TRUE about most project life cycles?

  1. Staffing level is highest at the start.
  2. The stakeholders' influence is highest at the start.
  3. The level of uncertainty is lowest at the start.
  4. The cost of changes is highest at the start.

Answer(s): B



An input required in Define Scope is an organizational:

  1. structure.
  2. process asset.
  3. matrix.
  4. breakdown structure.

Answer(s): B



What cost control technique is used to compare actual project performance to planned or expected performance?

  1. Cost aggregation
  2. Trend analysis
  3. Forecasting
  4. Variance analysis

Answer(s): D



What is the term assigned to products or services having the same functional use but different technical characteristics?

  1. Scope
  2. Quality
  3. Specification
  4. Grade

Answer(s): D



When is a Salience Model used?

  1. In a work breakdown structure (WBS)
  2. During quality assurance
  3. In stakeholder analysis
  4. During quality control (QC)

Answer(s): C