What are the performance measurements for the Schedule Control process?

  1. SV (EV - PV) and SPI (EV ÷ PV)
  2. SV (PV - EV) and SPI (PV ÷ EV)
  3. SV (EV - BAC) and SPI (EV ÷ BAC)
  4. SV (EV - AC) and SPI (EV ÷ AC)

Answer(s): A

Explanation:

Schedule variance is (EV - PV) and schedule performance index is (EV ÷ PV).



The work that must be done in order to deliver a product with the specified features and functions is:

  1. Project verification
  2. Project scope
  3. Project control
  4. Product scope

Answer(s): B

Explanation:

Project Scope: The work that must be done in order to deliver a product with the specified features and functions.



The project manager is assigned in the?

  1. Management Plan
  2. SOW
  3. Charter (contract)
  4. Project Plan

Answer(s): C

Explanation:

Project Manager should be assigned in the early phase of the project otherwise project may get delay.



Parametric Estimating is done as a part of which process:

  1. Estimate Activity Durations
  2. Sequence Activities
  3. Develop Schedule
  4. Estimate Activity Resources

Answer(s): A

Explanation:

Tools and Techniques for Estimate Activity Durations are: Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.



Make payment to seller is done in _______ .

  1. Plan Procurements
  2. Conduct Procurements
  3. Administer Procurements
  4. Close Procurements

Answer(s): C

Explanation:

Make payment to seller is done in Administer Procurements.