You are the business analyst for a large project for your organization. Your project has 65 stakeholders and this will greatly increase the complexity of the communication in this project. To demonstrate how complex this project and its communication will be, you show the management the number of communication channels in this project. How many channels exist in this project based on the number of stakeholders?
Answer(s): D
Explanation:
There are 2,080 communication channels in this project. You can find the number of communication channels by using the formula N(N-1)/2 where N represents the number of stakeholders. Answer B is incorrect. This is simply 65 times 65. Answer A is incorrect. This is simply 65 times 64.
Answer C is incorrect. This is the number of identified stakeholders.