The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis.
What time management activity should be done NEXT?

  1. Update resource requirements
  2. Recommend corrective actions
  3. Estimate Activity Durations
  4. Create a milestone list

Answer(s): A



If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?

  1. Perform a Monte Carlo analysis.
  2. Fast track the project.
  3. Perform resource leveling.
  4. Analyze the life cycle costs.

Answer(s): C



A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours per installation from past projects to predict the future.
This is an example of which of the following?

  1. Parametric estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Monte Carlo analysis

Answer(s): A



In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:

  1. Risk impact of crashing each activity.
  2. Customer's opinion of which activities to crash.
  3. Boss's opinion of which activities to crash and in which order.
  4. Project life cycle phase in which the activity is due to occur.

Answer(s): A