Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?
- It would increase the critical path.
- Communication would be more complex.
- There would be no effect.
- It would delay activity F.