Which stage of the change management process deals with what should be done if the change is unsuccessful?

  1. Remediation planning
  2. Categorization
  3. Prioritization
  4. Review and close

Answer(s): A



Which of the following items would commonly be on the agenda for a change advisory board (CAB)?
1. Details of failed changes
2. Updates to the change schedule
3. Reviews of completed changes

  1. All of the above
  2. 1 and 2only
  3. 2 and 3 only
  4. 1 and 3 only

Answer(s): A



Which of the following statements is CORRECT for every process?
1. It delivers its primary results to a customer or stakeholder
2. It defines activities that are executed by a single function

  1. Both of the above
  2. 1 only
  3. Neither of the above
  4. 2 only

Answer(s): B



Which of the following are benefits to the business of implementingservice transition?
1. Better reuse and sharing of assets across projects and resources
2. Reduced cost to design new services
3. Result in higher volume of successful changes

  1. 1 and 2 only
  2. 2 and 3 only
  3. 1 and 3 only
  4. None of the above

Answer(s): C



Remediation planning is BEST described in which of the following ways?

  1. Planning how to recover the cost of a change
  2. Planning the steps required to be taken if a change is unsuccessful
  3. Planning how to compensate a user for a failed change
  4. Planning how to advise the change requestor of a failed change

Answer(s): B



Viewing page 39 of 105
Viewing questions 191 - 195 out of 519 questions