Free PDM_2002001060 Exam Braindumps (page: 8)

Page 7 of 54

What is the correct GIC to plan costs related to payment of a subcontractor responsible for BTS commissioning?

  1. 7331 Implementation.
  2. 7332 site acquisition.
  3. 7348 project management.
  4. 7333 construction works.

Answer(s): A



Which one of the following is NOT a risk?

  1. Customer might run into environmental issues with the municipality due to our product and missing ISO1 4000 certification.
  2. Oursubcontractor might charge us for the extra site visits as this particular case is not written down in our supply contract.
  3. Logistic has informed the project team that the delivery which was expected last week has not arrived yet.
  4. The acceptance criteria in the contract amendment might lead to additional effort as the wording could be misunderstood.

Answer(s): C



What is NOT a cost category based on the Nokia cost management guideline?

  1. Base costs.
  2. Resource costs.
  3. Risk contingency costs.
  4. Non conformance costs.

Answer(s): B



Who is responsible for presenting the project financial results in the project review meetings?

  1. Project Manager with support of the costand progress manager.
  2. Cost and progress manager and project controller.
  3. Cost and progress manager with support of the project manager.
  4. Project controller.

Answer(s): A






Post your Comments and Discuss Nokia PDM_2002001060 exam with other Community members:

PDM_2002001060 Discussions & Posts