Which of the following is an advantage of site based operations (back -to-back ordering and invoicing of site based actMties):

  1. subcontractors will not have to wait for customer acceptance in order to get paid for their work.
  2. transactional processes can be automated thus reducing Logistics costs.
  3. there will not be any additional project management overhead.
  4. NCC and materialized risk will only occur at a site level.

Answer(s): B



What are the defined gates in the Nokia Sales Work Flow?

  1. Customer Selection, Go/No Go, Bid/No Bid, Approval/No Approval, Deal/No Deal, Start Delivery.
  2. Receive the RFQ, Define Bid Team, Create Customer Offer, Negotiate Contract, Prepare Project Plan.
  3. Identify Customer Needs, Develop Solution, Prepare Commercial Offer, Negotiate Contract, Prepare PTA.
  4. Receive RFQ, Develop Solution, Prepare Commercial Offer, Negotiate Contract, Prepare for Delivery.

Answer(s): A



What is RTI?

  1. The interface between the site quality and progress modules of IPM.
  2. The interface between SAP and IPM.
  3. An external database linking SAP and business objects reporting.
  4. The interface between the change management and progress modules of IPM.

Answer(s): B



Change management does NOT enable:

  1. the capability to refilect changes in project ETC once the cost of changes are known.
  2. proactive management of the cost impact ofa change.
  3. consolidated and automated GS reporting of change costs across business lines.
  4. change in SAP transactions.

Answer(s): D