What will be the resulting performance index if the actual cost is higher than the earned value?

  1. Cost performance Index (CPI) is greaterthan 1.
  2. Schedule performance Index (SPI) is lower than 1.
  3. Cost performance Index (CPI) is lower than 1.
  4. Schedule performance Index (SPI) is greaterthan 1.

Answer(s): C



CompanyA is working on a project. The project`s budget is 610,000. The planned value as of date X is 64,000. The project is 30% completed. 60% of the budget has been spent to date X. The Earned Value (EV) of the project is:

  1. 6600.
  2. 63,000.
  3. 65,000.
  4. 66,000.

Answer(s): B



Which of the following examples are effective results of a correctly performed root cause analysis?

  1. Missing method-of-procedure (MOP) and therefore no rollback procedures available for the site.
  2. Health and safety regulations were unclearto the Nokia team.
  3. Incorrect overtime booking.
  4. Gap in communication between the project team and the sales team.

Answer(s): A



CompanyA is working on a project. The project`s budget is 610,000. The Planned value as of date X is 64,000. The project is 30% completed. 60% of the budget has been spent. If the company continues to spend money at the same rate, what will the project cost (EAC)?

  1. 610,000.
  2. 620,000.
  3. 66,000.
  4. 4,000.

Answer(s): B



What is the correct GIC to plan costs related to payment of a subcontractor responsible for BTS commissioning?

  1. 7331 Implementation.
  2. 7332 site acquisition.
  3. 7348 project management.
  4. 7333 construction works.

Answer(s): A