Which type of chart is a graphic representation of a process showing the relationships among process steps?
Answer(s): C
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Answer(s): D
Which tool and technique is used in Conduct Procurements?
What provides information regarding the ways people, teams, and organizational units behave?
Answer(s): B
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
5.4.2.1 DecompositionDecomposition is a technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. The work package is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed. The level of decomposition is often guided by the degree of control needed to effectively manage the project. The level of detail for work packages will vary with the size and complexity of the project. Decomposition of the total project work into work packages generally involves the following activities:Identifying and analyzing the deliverables and related work; Structuring and organizing the WBS;Decomposing the upper WBS levels into lower-level detailed components; Developing and assigning identification codes to the WBS components; and Verifying that the degree of decomposition of the deliverables is appropriate.