Which of the following is an input to the Direct and Manage Project Execution process?

  1. Approved change requests
  2. Approved contract documentation
  3. Work performance information
  4. Rejected change requests

Answer(s): A



Which of the following factors is lowest at the start of the project?

  1. Cost of changes
  2. Stakeholder influences
  3. Risk
  4. Uncertainty

Answer(s): A



In which domain of project management would a Pareto chart provide useful information?

  1. Project Scope Management
  2. Project Time Management
  3. Project Communications Management
  4. Project Quality Management

Answer(s): D



Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

  1. Conduct Procurements.
  2. Close Procurements.
  3. Administer Procurements,
  4. Plan Procurements.

Answer(s): C



In which process might a project manager use risk reassessment as a tool and technique?

  1. Perform Qualitative Risk Analysis
  2. Monitor and Control Risk
  3. Monitor and Control Project Work
  4. Plan Risk Responses

Answer(s): B